Posts Tagged ‘MetroBus build’

Woods Estate Agents, Bradley Stoke, Bristol

MetroBus build: September report

Posted on Wednesday 4th October 2017 at 9:47 pm by SH (Editor)

Photo of traffic using the new bus lane at the southern end of Bradley Stoke Way.

By Jim Aitken, community liaison officer at Alun Griffiths Ltd.

South of Patchway Brook

Traffic management has now been removed, with the exception of one final section near Primrose Bridge, which has been left in place so that a pollution control chamber can be installed. We await the design solution to install this equipment as the underground utilities that are there prevent the current planned installation.

An evening road closure from Patchway Brook to Savages Wood has been applied for to undertake some additional slot cutting within the carriageway outside the leisure centre. At the time of writing, it was hoped to undertake this work on one night only during the week commencing 25th September, from 8pm to midnight.

Great Stoke Roundabout

Traffic has been switched to the new bus lane to enable works on the northbound side, including new kerbs lines, drainage and footway works. Local pedestrian footway diversions around The Worthys will be installed to facilitate these works. Works including surfacing is to be completed early October for this area, with the road being fully cleared of traffic management by the end of October.

The overall duration of works has extended due to drainage design changes. We have strived to keep the traffic flowing by keeping open narrow lanes, as opposed to other traffic management measures which could have restricted traffic movement. Consequently, we have received no complaints of traffic congestion in this area whilst we have completed the extended work on the verge.

More: Stoke Gifford By-Pass work set to be completed by December »

Share this article:

Discussion is open - be the first to comment - click here to respond.

UK_Best stuff in your city_468x60

MetroBus construction report (August 2017)

Posted on Tuesday 5th September 2017 at 9:15 pm by SH (Editor)

Photo of new bus lane near Great Stoke Roundabout.

By Jim Aitken, community liaison officer at Alun Griffiths Ltd.

All Alun Griffiths works at Aztec West, Bradley Stoke Way north of Patchway Brook Roundabout (near Aldi) and around Webbs Wood Roundabout are complete.

South Gloucestershire Council continues to work in the vicinity of Aztec West on the separate (i.e. non-MetroBus) A38 southbound widening and roundabout improvement scheme.

South of Patchway Brook

Traffic management has now been removed, with the exception of one final section near Primrose Bridge, which has been left in place so that a pollution control chamber can be installed. Trial trenching has now completed to determine the service(s) that will need to be worked around, if possible. Subject to design changes and approvals, this will take us up to the end of September.

Great Stoke Roundabout

At the southern end of Bradley Stoke Way, on the approach to Great Stoke Roundabout (a.k.a. Rabbit Roundabout), the new bus lane area is now complete up to binder course. Only the final surface course of tarmac remains to be done, followed by lining.

During early September, traffic will be switched to the new bus lane to enable works on the northbound side, including new kerbs lines, drainage and footway works. Local pedestrian footway diversions around The Worthys will be installed to facilitate this.

All work in this area, including surfacing, is to be completed by early October.

The overall duration of works has extended due to drainage design changes. We have strived to keep the traffic flowing by keeping open narrow lanes, as opposed to other traffic management measures which could have restricted traffic movement. Consequently, we have received no complaints of traffic congestion in this area whilst we have completed the extended work on the verge.

More: Stoke Gifford By-Pass set for completion in October »

Share this article:

Discussion is open - 1 comment (view) - click here to respond.

SGC hit by a further £2.8 million overspend on MetroBus build

Posted on Wednesday 19th July 2017 at 11:07 pm by SH (Editor)

MetroBus construction at Woodlands Lane: Gas main and complex cable ducting have caused delays.

South Gloucestershire Council (SGC) has been dealt a further body blow to its finances with the news that construction of the North Fringe to Hengrove Package (NFHP) MetroBus scheme is now projected to come in nearly £16m over budget, an increase of £4.6m since the last figures were released in November 2016.

The latest numbers, originating from the MetroBus Project Review Board, are revealed in a report that was due to be considered by SGC’s Cabinet on 10th July.

The estimated total cost of the project, which is jointly funded by central government, SGC and Bristol City Council, is now put at £117.9m, up 15.8% on the original budget of £101.8m.

Because of the way the funding is arranged, with the government contribution being fixed at £51.1m and SGC committed to covering 61 percent of the remainder, SGC’s projected total contribution has now risen to £40.3m, up 32.1% on its original budget of £30.5m.

Reasons given for the latest increase in forecast cost include:

  • Additional delays to the completion of Bradley Stoke Way, due to further unforeseen utility diversion work
  • Additional earthwork requirements on the Stoke Gifford Transport Link (SGTL) and the Ham Brook Bridge
  • Additional delay costs to the SGTL due to interfaces with Network Rail
  • Delays in obtaining Highways England approvals for work on the M32
  • Delay costs and additional construction costs relating to piling in the city centre
  • Increases in project and site management costs due to the longer than expected duration of the project

More: £0.5m will be diverted from council’s revenue underspend »

Share this article:

Discussion is open - 1 comment (view) - click here to respond.

MetroBus construction: June progress report

Posted on Wednesday 12th July 2017 at 8:33 pm by SH (Editor)

Photo of temporary traffic lights in operation between the Great Meadow and Great Stoke roundabouts.

By Jim Aitken, community liaison officer at Alun Griffiths Ltd.

Bradley Stoke Way (BSW)

The Alun Griffiths compound at Woodlands Lane has now been cleared. Work on swales and landscaping is ongoing.

A38 south of Aztec West

The new MetroBus stops are now 100 percent complete and all traffic management for our works have been removed, however South Gloucestershire Council is still working in and around the Aztec West area. [See: Aztec West Roundabout A38 Southbound Widening Scheme]

South of Patchway Brook

The bus lane will remain closed to allow for various ongoing traffic management switches so that landscaping and re-profiling works to the swales and verges can be completed, along with turfing and further tree/shrub planting.

An additional catch pit has to be installed on the drainage system near Primrose Bridge where we have tied into the exiting drainage system for pollution control measures.

The reprofiling is due to be completed during July. Once works are complete, all road cones will be removed. Landscaping works will be ongoing throughout.

Great Stoke Roundabout

Earthworks and road excavation are both 95 percent complete and drainage installation has commenced.

There is a large drainage excavation required along the footway between Great Meadow and Great Stoke roundabouts. Design changes have been necessary due to underground services and the area required for root protection of a certain species of tree. A 4-metre deep excavation is required adjacent to the carriageway and a redesign has now been provided. This is different from our original scope, so twenty-four-hour two-way temporary traffic lights are now required to cover the area of approximately 40 metres of road. This will not affect access to The Worthys.

More: Latest on the construction of the Stoke Gifford By-Pass »

Share this article:

Discussion is open - be the first to comment - click here to respond.

0

Ocean Estate Agents, Bradley Stoke, Bristol.
MOT and servicing at LCM Automotive, Filton, Bristol.
The Bradley Stoke Journal magazine - your MONTHLY local newspaper.
Chiropractor, Patchway, Bristol BS34.