Photo of temporary traffic lights in operation between the Great Meadow and Great Stoke roundabouts.

MetroBus construction: June progress report

By Jim Aitken, community liaison officer at Alun Griffiths Ltd. Bradley Stoke Way (BSW) The Alun Griffiths compound at Woodlands Lane has now been cleared. Work on swales and landscaping is ongoing. A38 south of Aztec West The new MetroBus stops are now 100 percent complete and all traffic management for our works have been removed, however South Gloucestershire Council is

Continue reading
MetroBus construction work at the southern end of Bradley Stoke Way.

MetroBus to introduce 24-hour temporary traffic lights on BSW from Monday

Motorists using the southern end of Bradley Stoke Way (BSW) could be faced with extra delays for the next two weeks after MetroBus contractors Alun Griffiths announced they will need to introduce 24-hour temporary traffic lights on the approach to Great Stoke Roundabout (a.k.a. Rabbit Roundabout). The company had previously given an assurance that temporary traffic lights, if needed at all in this

Continue reading
Photo of MetroBus construction work near Great Stoke Roundabout.

MetroBus build: May progress report

By Jim Aitken, community liaison officer at Alun Griffiths Ltd. Bradley Stoke Way (BSW) All carriageway surfacing is now complete, including road markings and anti-skid. Landscaping is now taking place along BSW to the verge and swale areas, forming the embankments’ profiles so they may receive turfing and planting – this is very weather dependent. It is our intention to

Continue reading
Artist's impression of a MetroBus stop with iPoint.

MetroBus operator announcement delayed (again)

The announcement about which company (or companies) will be operating services on Bristol’s new MetroBus network has been delayed once again, this time until after the general election on 8th June, the Journal can reveal. Last summer, a West of England Partnership spokesperson said that negotiations with potential operators were expected to conclude by mid-September (2016), but it was later

Continue reading
Photo of MetroBus construction work near Great Stoke Roundabout.

MetroBus construction: April progress report

By Jim Aitken, community liaison officer at Alun Griffiths Ltd. Bradley Stoke Way (BSW) Continuing the finishing works for this area, areas of anti-skid surface at the junction of Orchard Gate, Woodlands Lane and Patchway Brook Roundabout will be undertaken outside of peak hours (after 7pm) during May, due to the limited space available and potential traffic impact. Now the

Continue reading
The Woodlands Lane junction with Bradley Stoke Way, fully reopened after being closed for 559 days for MetroBus roadworks.

MetroBus project: February progress report

By Jim Aitken, community liaison officer at Alun Griffiths Ltd. Bradley Stoke Way On Tuesday 14th February, following just over four weeks of night time surfacing between the Aztec West and Patchway Brook roundabouts, and working jointly with South Gloucestershire Council’s (SGC’s) signalisation team, the traffic lights at the Woodlands Lane and Orchard Gate junctions were commissioned and switched on.

Continue reading