Posts Tagged ‘roadworks’

Woods Estate Agents, Bradley Stoke, Bristol

Ring Road traffic hell set to start on Monday

Posted on Friday 21st July 2017 at 6:43 pm by SH (Editor)

The two Bromley Heath Viaducts which carry the A4174 Ring Road over the River Frome.

Commuters in north Bristol are being warned to expect significant additional delays on roads throughout the area when South Gloucestershire Council (SGC) commences repairs to the Bromley Heath Viaduct in the final week of July.

The A4174 Ring Road near Hambrook is to be reduced to 50 percent capacity (one lane each way instead of two) for an estimated 33 weeks from the weekend of 22nd/23rd July.

The project was originally expected to take 52 weeks to complete, but a recent decision by the West of England Joint Committee to allocate additional funding of £2.8m means that it has been possible to reduce its duration. This will be achieved by carrying out the work over dual weekday shifts, with some weekend work as and when required.

Cllr Colin Hunt, SGC Cabinet member responsible for transport, said:

“Reducing the length of the work will help to alleviate congestion and the impact of diversions on local communities, commuters and people travelling through the area. We know the scheme will cause significant disruption for people but we are trying everything we can to mitigate this.”

The work is required in order to undertake essential maintenance on one of two parallel viaducts that carry the road over the River Frome between the Hambrook lights and Bromley Heath Roundabout.

The southern viaduct, which carries the westbound carriageway, is in need of: pier strengthening, bearing replacement, drainage improvements, waterproofing, parapet and safety fence replacement, concrete repairs, and abnormal load carrying capacity improvements.

A separate major project to provide a wider shared path and a protective barrier for cyclists and pedestrians using the viaduct will be carried out concurrently with the repairs.

More: Points to note for Bradley Stoke commuters »

Share this article:

Discussion is open - 1 comment (view) - click here to respond.

UK_Best stuff in your city_468x60

Overnight closures of A38 and Aztec West Roundabout from Monday

Posted on Sunday 16th July 2017 at 1:00 pm by SH (Editor)

Photo of matrix sign at Aztec West.

Over the last few weeks, South Gloucestershire Council’s traffic signals team have been installing new traffic signals infrastructure to replace the old equipment on the Aztec West Roundabout. It was anticipated that these works would be substantially completed and the new equipment turned on by the first week in July. The new left-turn MetroBus lane between Bradley Stoke Way and the A38 southbound will remain closed whilst commissioning and final snagging works are carried out.

The completion date for the Aztec West Roundabout / A38 Widening Scheme delivered by StreetCare is Autumn 2017. StreetCare will be undertaking the resurfacing of the A38 between M5 J16 and the Aztec West roundabout from Monday 17th July for a period of three weeks. The work is being done overnight between 8pm and 6am to minimise disruption and will involve closing the A38 northbound and southbound. Advance signing and diversions for traffic will be in place.

• More information: www.southglos.gov.uk/A38roundaboutwidening

Latest information from SGC (14th July)

The areas to be resurfaced (and requiring road closures) will be as follows:

  • A38 southbound From M5 Junction 16 to Aztec West Roundabout
  • A38 northbound From Aztec West Roundabout to M5 Junction 16
  • Aztec West roundabout circulatory.

Some or all of the above roads may be closed at any one time.

All traffic exiting Bradley Stoke Way at Aztec West roundabout will be required to turn left (south) down the A38 and follow appropriate diversions.

There will always be access and egress maintained to Park Avenue (Aztec West Business Park).

More: Details of bus service diversions »

Share this article:

Discussion is open - 3 comments (view) - click here to respond.

MetroBus construction: June progress report

Posted on Wednesday 12th July 2017 at 8:33 pm by SH (Editor)

Photo of temporary traffic lights in operation between the Great Meadow and Great Stoke roundabouts.

By Jim Aitken, community liaison officer at Alun Griffiths Ltd.

Bradley Stoke Way (BSW)

The Alun Griffiths compound at Woodlands Lane has now been cleared. Work on swales and landscaping is ongoing.

A38 south of Aztec West

The new MetroBus stops are now 100 percent complete and all traffic management for our works have been removed, however South Gloucestershire Council is still working in and around the Aztec West area. [See: Aztec West Roundabout A38 Southbound Widening Scheme]

South of Patchway Brook

The bus lane will remain closed to allow for various ongoing traffic management switches so that landscaping and re-profiling works to the swales and verges can be completed, along with turfing and further tree/shrub planting.

An additional catch pit has to be installed on the drainage system near Primrose Bridge where we have tied into the exiting drainage system for pollution control measures.

The reprofiling is due to be completed during July. Once works are complete, all road cones will be removed. Landscaping works will be ongoing throughout.

Great Stoke Roundabout

Earthworks and road excavation are both 95 percent complete and drainage installation has commenced.

There is a large drainage excavation required along the footway between Great Meadow and Great Stoke roundabouts. Design changes have been necessary due to underground services and the area required for root protection of a certain species of tree. A 4-metre deep excavation is required adjacent to the carriageway and a redesign has now been provided. This is different from our original scope, so twenty-four-hour two-way temporary traffic lights are now required to cover the area of approximately 40 metres of road. This will not affect access to The Worthys.

More: Latest on the construction of the Stoke Gifford By-Pass »

Share this article:

Discussion is open - be the first to comment - click here to respond.

MetroBus to introduce 24-hour temporary traffic lights on BSW from Monday

Posted on Sunday 11th June 2017 at 8:34 pm by SH (Editor)

MetroBus construction work at the southern end of Bradley Stoke Way.

Motorists using the southern end of Bradley Stoke Way (BSW) could be faced with extra delays for the next two weeks after MetroBus contractors Alun Griffiths announced they will need to introduce 24-hour temporary traffic lights on the approach to Great Stoke Roundabout (a.k.a. Rabbit Roundabout).

The company had previously given an assurance that temporary traffic lights, if needed at all in this location, would only be used at off-peak times.

The change of plan is said to be a consequence of design changes which require additional excavation work to be carried out.

A spokesperson for Alun Griffiths said:

“A large drainage excavation is required along the footway between Great Meadow and Great Stoke Roundabouts. Design changes are required due to underground services and the area required for root protection of certain species of tree. A 4m-deep excavation is required adjacent to the carriageway and a redesign has now been provided. This is different from our original scope, so 24-hour two-way temporary traffic lights are now required to cover the area of approximately 40 metres of road. This will not affect access to The Worthys.”

“To complete this work as safely as possible we will need to close the southbound lane at this point and use temporary traffic lights for a period of two weeks. We shall endeavour to complete this work and remove the traffic management earlier than the two-week period. Currently we are seeking to begin this work from Monday 12th June until Friday 23rd June. The lights will be manually controlled during peak hours 7am-9.30am and 3.30pm-6pm.

“We apologise for any inconvenience caused during this time.”

The news comes just weeks after Alun Griffiths announced that work in the same area had been “re-sequenced”, meaning that it will now extend into August instead of being finished by the end of May (the scheduled completion date given at a public meeting in January).

Related links:

Share this article:

Discussion is open - 5 comments (view) - click here to respond.

0

Ocean Estate Agents, Bradley Stoke, Bristol.
Office accommodation at Courtyard Offices, Bradley Stoke, Bristol.
The Bradley Stoke Journal magazine - your MONTHLY local newspaper.
Chiropractor, Patchway, Bristol BS34.